Community Infrastructure
Building a sense of community and improving daily lifestyle in villages across the Umiam basin is an important mandate of the SPV Society. Community infrastructure includes all infrastructure that provides the residents with a platform for cultural, social and talent-related expression.
These include community durbar halls where villages can host events, meetings, community-related health and awareness campaigns and others. Sports and games facilities are also a part of the projects that come under community infrastructure.
Road Infrastructure
Owing to the mountainous terrain and hostile monsoons, transportation in the region is difficult as roadways and paths are constantly in need of repair. Some of the rural pockets still rely on dirt paths and trails for residents to travel to nearby places. The lack of good roadways is detrimental as it adds an economic burden to those who want to ferry produce to market centres and can be devastating during a health emergency. Generations have been living with such inconveniences and the SPV Society has earmarked some of its efforts to alleviate the conditions of the roads and pathways, including commissioning new ones.
Working together with established authorities and concerned line departments, the SPV Society identifies areas in the Umiam basin region where there is a need for up-gradation of roads, bridges and foot-paths. The Society then utilizes the funds at the ground level to ensure that the raw materials are sourced and the labour is mobilized.
Village Level Infrastructure Projects
1 | NONGTRAI | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
1 | Water Supply | 2013-14 | 100% | Completed | Work entrusted to MGCC |
2 | Construction of Community Hall | 2013-14 | 100% | Completed | Work entrusted to Nongtrai Durbar |
3 | Construction of Village playground | 2013-14 | 100% | Completed | Work entrusted to Nongtrai Sport Club |
4 | Nongtrai Govt L.P. School | 2013-14 | 100% | Completed | Work entrusted to Managing Committee |
5 | Nongtrai Sec. School, Nongtrai | 2013-14 | 100% | Completed | Work entrusted to Nongtrai Durbar |
6 | Construction of Footpath | 2013-14 | 100% | Completed | Work entrusted to Nongtrai Durbar |
7 | Approach road to Community hall | 2013-14 | 100% | Completed | Work entrusted to MGCC |
8 | Improvement and widening of existing football ground | 2015-16 | 100% | Completed | Work entrusted to Nongtrai Durbar |
9 | RCC & stone masonary | 2015-16 | 100% | Completed | Work entrusted to MGCC |
10 | Improvement of ground for parking lot, etc. | 2015-16 | 100% | Completed | Work entrusted to Nongtrai Durbar |
11 | Re-construction of damaged footpath | 2015-16 | 100% | Completed | Work entrusted to Nongtrai Durbar |
12 | Construction of CC footpath | 2015-16 | 100% | Completed | Work entrusted to Nongtrai Durbar |
13 | Improvement and widening of existing ground (Church meeting) | 2015-16 | 100% | Completed | Work entrusted to Nongtrai Sport Club |
14 | Construction of retaining wall etc. of Durbar Hall | 2015-16 | 100% | Completed | Work entrusted to MGCC |
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
15 | Construction of breast wall & laying of interlocking lanes | 2015-16 | 100% | Completed | Work entrusted to MGCC |
16 | Construction of bathrooms (6nos.) | 2015-16 | 100% | Completed | Work entrusted to MGCC |
17 | Weaving centre | 2017-18 | 100% | Completed | Work entrusted to Nongtrai Durbar |
18 | Solar street Lighting | 2017-18 | 100% | Completed | Work entrusted to Nongtrai Durbar |
19 | Community Bus | 2017-18 | 100% | Completed | Work entrusted to Nongtrai Durbar |
TOTAL | 100% |
2 | TYNGNER | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
1 | Water Supply | 2013-14 | 100% | In Progress | Work entrusted to MGCC |
2 | Construction of Community Hall | 2016-17 | 90% | In Progress | |
3 | Tyngner L.P. School | 2014-15 | 100% | Completed | |
4 | Construction of Footbridge | 2013-14 | 100% | Completed | |
TOTAL | 98% |
3 | DEWSAW | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
1 | DEWSAW L.P. School | 2013-14 | 100% | Completed | |
2 | Dewsaw Nongthymmai L.P. School | 2013-14 | 100% | Completed | |
TOTAL | 100% |
4 | NONGLAIT | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
1 | Nonglait L.P. School | 2014-15 | 100% | Completed | |
2 | Construction of Footbridges | 2013-14 | 100% | Completed | |
TOTAL | 100% |
5 | LAWBAH | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
1 | Lawbah L.P. School | 2017-18 | 100% | Completed | |
2 | Solar street Lighting | 2013-14 | 80% | In Progress | |
TOTAL | 90% |
6 | MAWDON | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
1 | Construction of Footbridges (2nos) | 2017-18 | 100% | Completed | (Work entrusted to BADD) |
TOTAL |
7 | SHELLA | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
1 | Construction of Community Hall (Jasir) | 2013-14 | 100% | Completed | Final instalment due |
2 | Construction of Playground (Pyrkan) | 2013-14 | 100% | Completed | Final instalment due |
TOTAL | 100% |
8 | MAWRYNGKHONG | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
1 | Construction of Community Hall | 2014-15 | 100% | Completed | |
2 | Mawryngkhong L.P. School | 2014-15 | 100% | Completed | |
3 | Construction of C.C footpath,C.C Drain (small), big drain, drain on a rocky slope with dowel bar,drinking water reservoir, providing railing, construction of R/wall repairing of existing damage footpath step. | 2017-18 | 65% | In Progress | |
TOTAL | 88% |
9 | LAIKHER (NONGNONG,RYNSONGKATONOR,NONGRUM) | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
1 | Construction of Big drain,protection wall of old monument providing retaining wall,rail post,railing and other repairing works at NONGNONG | 2017-18 | 45% | In Progress | |
2 | Construction of C.C Footpath,Retaining wall,Big drain,providing railing,repairing steps at RYNGSONGKATONOR | 2017-18 | In Progress | ||
3 | Construction of Footpath,Retaining wall,Big drain,Household small drain ,providing rail post with G.I pipe railing,repairing damaged foothpath at NONGRUM | 2017-18 | In Progress | ||
TOTAL | 15% |
10 | JASIR (JASIR,JAMEW,DUBA,DISONG) | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
1 | Construction of Big drain,C.C Footpath,Water tank providing rail post with G.I pipe railing,repairing damaged foothpath at JASIR | 2017-18 | In Progress | -₹ 2.94 | |
2 | Construction of big drain,catch water drain, repairing of damaged footpath providing rail post railing at Jamew | 2017-18 | In Progress | ₹ 1.91 | |
3 | Construction of Big Drain and Retaining wall at Duba | 2017-18 | In Progress | ||
4 | Construction of big drain, retaining wall etc. at Disong (Shella) | 2017-18 | In Progress | ||
5 | Construction of RKM Sec. School at DISONG | 2014-15 | 100% | Completed | |
6 | Construction of RKM Hr. Sec. School at DISONG | 2017-18 | 45% | In progress | |
TOTAL | 24% |
11 | PYRKAN | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
1 | Construction of C.C footpath including Railing | 2017-18 | 100% | Completed | Final instalment due |
2 | Construction of Long Round Road Including MBT at Pyrkan Village (L=2.15 Km) | 2013-14 | 100% | Completed | Work entrusted to MGCC |
3 | Construction of RKM LP & UP School | 2017-18 | 15% | In progress | |
TOTAL | 72% |
12 | SOHLAP | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
1 | Construction of Community Hall | 2014-15 | 100% | Completed | |
2 | Construction of U.P School Building | 2016-17 | 100% | Completed | |
3 | ConstructionR.C.C Retaining wall in between Presbyterian Church & residential locality | 2017-18 | 100% | Completed | |
4 | Construction of C.C Footpath, c.c drain, footbridge,culverts,Retaining Wall | 2017-18 | In Progress | ||
5 | Construction of Big drain, c.c drain, and pavement incl. Wall fencing at St. Xaviers, Sohlap | 2017-18 | 95% | In Progress | |
6 | Repair & Imp. of Suspension bridge | 2017-18 | 100% | Completed | Work entrusted to BADD |
7 | Construction of additional item of work for Community Hall at Sohlap, Shella. | 2016-17 | 100% | Completed | |
TOTAL | 85% |
13 | MUSTOH | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
1 | Construction of Playground | 2013-14 | 95% | In Progress | |
2 | Sun Beam L.P School | 2013-14 | 100% | Completed | |
TOTAL | 98% |
14 | SAWKHER (LUM-U-SMON, SAIKARAP, JATAP, SAISOHPHAN) | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
1 | Construction of RKM LP & UP School | 2017-18 | 15% | In progress | |
2 | Construction of Footpats | 2013-14 | 100% | Completed | |
TOTAL | 58% |
15 | NONGWAR | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
1 | Construction of Playground | 2013-14 | 100% | Completed | |
2 | Construction of RKM Sec. School | 2013-14 | 100% | Completed | |
3 | Construction of RKM Hr. Sec. School | 2017-18 | 55% | In progress | |
TOTAL | 85% |
16 | LAITKYNSEW | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
1 | Laitkynsew Presbyterian L.P School | 2013-14 | 100% | Completed | |
2 | St Dominic Savio U.P School | 2013-14 | 100% | Completed | |
3 | St Dominic Savio L.P School | 2013-14 | 100% | Completed | |
TOTAL | 100% |
17 | TYRNA | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
1 | Construction of RKM LP & UP School | 2017-18 | 65% | In progress | |
2 | Public Sanitation | 2017-18 | 35% | In Progress | Work entrusted to BADD |
TOTAL | 50% |
18 | RUMNONG | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
1 | Construction of RKM LP & UP School | 2017-18 | 5% | In progress |
19 | GENERAL ECONOMY | ||||
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
Construction of Roads: (Work entrusted to PWD) | |||||
1 | Shella Bazar-Shella Road | 2016-17 | 100% | Completed | Work entrusted to PWD ® SOHRA |
2 | Approach Road to Sohlap (Football ground) | 2016-17 | 100% | Completed | Work entrusted to PWD ® SOHRA |
3 | Imp. of Laitkynsew-Mustoh Road | 2016-17 | 100% | Completed | Work entrusted to PWD ® SOHRA |
4 | Imp. etc. of approach Road at Mawlyngbna | 2016-17 | 100% | Completed | Work entrusted to PWD ® MAWSYNRAM |
5 | Imp. etc. of Mawsynram-Hat Mawdon Road | 2016-17 | 100% | Completed | Work entrusted to PWD ® MAWSYNRAM |
4 | Rep. & imp. of sus. bridge at Mawryngkhong (Shella) | 2017-18 | 100% | Completed | Work entrusted to PWD ® MAWSYNRAM |
TOTAL | 100% |
Sl. No. | Name of Scheme/Project | Year of Sanction | PHYSICAL STATUS OF PROJECT | STATUS OF WORK | REMARK |
IRRIGATION: (Work entrusted to Water Resources Department) | |||||
1 | Flood protection & anti erosion work AT Pyrkan | 2017-18 | 50% | In Progress | Work entrusted to Water Resources department |